64 firms vie for 900MW 5th phase of MBR Solar Park

By DG Staff

The Mohammed bin Rashid Al Maktoum Solar Park in Dubai is the largest single-site solar park in the world, with a planned capacity of 1,000MW by 2020, and 5,000MW by 2030, with a total investment of Dh50 billion..

DUBAI 16 June 2019: Dubai Electricity and Water Authority (Dewa) has issued a tender for the 5th phase of the Mohammed bin Rashid Al Maktoum Solar Park for 900 megawatts (MW) of electricity using photovoltaic solar panels, based on the Independent Power Project (IPP) model.

The deadline to submit the tenders is 22 August 2019. The winning bid will own 40% of the company operating the project, and Dewa will own 60%. The winning bidder will sign an agreement with Dewa to purchase the generated power for 25 years. Dewa received letters of intent for the tender from 64 companies. The fifth phase of the solar park will be commissioned in stages starting from Q2 2021.

The move supports the objectives of the Dubai Clean Energy Strategy 2050 to provide 75% of Dubai’s total power output from clean energy by 2050.

Largest single-site solar park

The Mohammed bin Rashid Al Maktoum Solar Park is the largest single-site solar park of its kind in the world. It will have a capacity of 5,000 MW by 2030 with investments of Dh50 billion. Through its projects, the park will accelerate Dubai’s expansion of solar power.

Saeed Mohammed Al Tayer, Dewa MD & CEO, said: “Dewa is working to transform Dubai into a global hub for clean energy and green economy, to make it the city with the lowest carbon footprint in the world. Meeting the clean energy objectives requires a capacity of 42,000MW of clean and renewable energy by 2050. To achieve our vision to become a globally-leading sustainable innovative corporation, we are working to establish sustainability as the roadmap that secures a brighter and happier future for Dubai, by launching major world-class initiatives and projects in green development.”

The 13MW first phase became operational in 2013 using photovoltaic solar panels. The 200MW photovoltaic second phase of the solar park was operational in March 2017. The 800MW photovoltaic third phase will be operational by 2020. The fourth phase of the solar park is the largest single-site Concentrated Solar Power (CSP) project in the world based on IPP, at a total investment of AED15.78 billion. The fourth phase of the 950MW hybrid power plant will use three technologies: 600MW from a parabolic basin complex, 100MW from a solar tower, and 250MW from photovoltaic panels. The project will feature the tallest solar tower in the world, 260 metres tall, and the largest thermal storage capacity of 15 hours; generating power around the clock.