Dubai’s Tripoli St to be the ‘parallel road’ to Airport Street

DUBAI 26 August 2018:  Dubai’s Tripoli Street Improvement Project has reached 60 per cent completion according to the Roads & Transport Authority (RTA).

Mattar Al Tayer, RTA Director-General and Chairman, said the 12-km long street links Sheikh Mohammed bin Zayed Road and Emirates Road will act as a parallel road to the Airport Road. The project is expected to be completed and opened in full in the first half of 2019.

“The new project will increase the street’s intake to about 12,000 vehicles per hour in both directions (6,000 vehicles per hour per direction) and ease the traffic flow on this corridor by 30 per cent. Upon completion, the project will act as a parallel to Al Amardi–Al Khawaneej Streets as well as Al Awir-Ras Al Khor Streets,” noted Al Tayer.

Work is progressing well and the completion rate has exceeded 90% in the extension of Tripoli St. (from Sheikh Zayed bin Hamdan Al Nahyan St. to Emirates Road). Completion rate has reached 95% in the flyover of Tripoli and Sheikh Zayed bin Hamdan Streets, 40% in the bridge linking with Sharjah-bound Emirates Road, 50% in the intersection of Tripoli-Nouakchott Streets, and 10% in the tunnel at the intersection of Tripoli-Algiers Streets (Mirdif-Warqaa).

Project Components

The project includes the widening of Tripoli Street over a 6.5 km stretch from the intersection with the Sheikh Mohammed bin Zayed Road (nearby Mirdif City Center) up to the Sheikh Zayed bin Hamdan Street.

It also includes the construction of a new 5.3 km-long road of three lanes in each direction from the intersection of Tripoli-Sheikh Zayed bin Hamdan Streets up to the Emirates Road.

“Thus, the overall length of the street will be around 12 km,” added Al Tayer.

The project also covers the development of interchanges across the street starting with the upgrading the junction of Tripoli-Algiers Streets to a tunnel of three lanes in each direction to serve the traffic flow inbound from Al Rabat St heading to Tripoli St, besides upgrading the current at-grade signalized intersection.

With the completion of these works, the waiting time at the existing intersection is expected to drop from three minutes to less than one minute. The project also includes upgrading the existing R/A at the intersection of Tripoli- Nouakchott streets to a bridge of three lanes in each direction.

It also includes improving the existing at-grade signalized junction, and transforming the intersection of Tripoli- Sheikh Zayed bin Hamdan Streets into a flyover to ensure a smooth traffic flow in all directions, in addition to the construction of collector roads to serve turn movements, and widening the camel underpass No (3) on Emirates Road.

It also includes widening the Tripoli St and improvements nearby Bel Remiatha Club and two signalized junctions to replace the existing R/As at Muhaisina.

The project also includes the construction of a three-lane bridge to serve the traffic from Tripoli St. to Emirates Road in the direction of Sharjah, and a surface intersection (entry/exit) for the traffic inbound from Sharjah heading to Emirates Road.