Unit 1 of Barakah Nuclear Plant reaches 50% power capacity

DG Staff

Al Barakh Nuclear Power Plant

ABU DHABI 23 September 2020: Nawah Energy Company has announced that the reactor of Unit 1 of the Barakah Nuclear Energy Plant has achieved 50 percent of its electricity production capacity.

The milestone achievement was announced on the sidelines of the 64th Annual Regular Session of the IAEA General Conference in Vienna, where the UAE hosted a side event entitled ‘UAE Peaceful Nuclear Energy Programme: The Journey’.

Reaching 50 percent power at Unit 1 of Barakah is an important step in the process of Power Ascension Testing, PAT, and comes at a historic time for the UAE Peaceful Nuclear Energy Programme, one month after the safe and successful completion of the synchronization of Unit 1 to the UAE transmission grid and the dispatch of the first megawatts of clean electricity from the Barakah Plant to the nation, said official news agency Wam.

Mohamed Ibrahim Al Hammadi, Chief Executive Officer of ENEC, said, “The UAE is now producing clean, baseload electricity through Unit 1 of the Barakah Plant, and the Unit has now achieved 50 percent power as part of the Power Ascension Testing our teams at Nawah are currently undertaking. Safety and quality-led progress is continuing to be made across all four Units of the Plant, and we are delighted to participate in the IAEA General Conference to share the latest updates with our industry partners on this strategic clean energy infrastructure project for the UAE.”

A delegation from the UAE including Hamad Al Kaabi, UAE Permanent Representative to the IAEA; Mohamed Ibrahim Al Hammadi, CEO of ENEC; Christer Viktorsson, Director General of the Federal Authority for Nuclear Regulations, FANR; and Ali Al Hammadi, CEO of Nawah, is currently participating in the 64th Annual Regular Session of the IAEA General Conference. It is being held from 21st – 25th September, 2020 at the Vienna International Centre in Vienna, Austria, and has brought together high-ranking officials and representatives from the IAEA Member States, both physically and virtually, to discuss a range of nuclear energy topics.

The UAE’s participation comes as Nawah gradually raises the power levels of Unit 1 of the Barakah Plant – over a number of months – as a part of the ongoing Power Ascension Testing. Throughout this process, the Unit’s systems are tested in line with national regulatory requirements and international best practice as the operations team safely makes progress towards full electricity production. Once the process is completed, Unit 1 will enter commercial operations and deliver abundant baseload electricity for up to 18 months prior to refuelling, demonstrating how efficient and reliable nuclear energy is at generating clean electricity 24/7.

The PAT is conducted under the oversight of the UAE’s independent nuclear regulator, the Federal Authority for Nuclear Regulations, FANR, which has now conducted more than 280 inspections since the start of Barakah’s development. This is in addition to more than 40 missions and assessments by the International Atomic Energy Agency, IAEA, and World Association of Nuclear Operators, WANO.

The Barakah Nuclear Energy Plant is the cornerstone of the UAE Peaceful Nuclear Energy Programme, which adheres to the highest international standards of safety, security, quality, transparency and non-proliferation. Through its role as the operator of the plant, Nawah is committed to ensuring the Barakah Plant is operated in line with all regulatory requirements and in full cooperation and collaboration with all relevant local, regional and international stakeholders.